Group delay on a VNA: what the trace means and three common mistakes

Started by LunaWei · 2026-10-13 23:27 UTC · 55 views · 2 replies
L Admin
Group delay is the negative derivative of phase with respect to frequency. On a VNA it answers a practical question: how much does the envelope of a narrowband signal get delayed through the DUT, and how flat is that delay across your channel.

Why engineers look at it
- Filters and cables with ripply phase create envelope distortion even when |S21| looks fine.
- In pulsed radar and digital radios, group-delay variation across the occupied bandwidth shows up as EVM or range sidelobes.
- Comparing two paths (for example main and diversity) needs matched delay, not only matched magnitude.

How to set the measurement
1. Calibrate with enough points that the phase unwrap is trustworthy. Sparse frequency grids make the derivative noisy.
2. Use a smoothing aperture that matches your channel bandwidth. Too narrow and the trace is noise; too wide and you average away real ripples.
3. Prefer a thru or TRL cal when absolute delay matters. SOLT with a poor definition of the thru standard shifts the absolute number even if relative ripples look right.

Three mistakes I see often
1. Reading absolute group delay from an uncorrected fixture. The coax and adapters dominate. Report relative variation across band, or de-embed first.
2. Ignoring wrap artifacts. If phase unwrap fails at a resonance, group delay spikes that are not physical. Zoom the span and raise the point count before trusting spikes.
3. Comparing DUTs at different temperatures or cable dress. A few degrees or a re-seated SMA can move absolute delay more than the DUT difference you care about.

Quick check before you trust the plot: terminate the DUT output (for a two-port) or replace the DUT with a known airline / delay line and confirm the VNA reports a delay close to the electrical length. If that fails, fix cal and fixtures before debugging the DUT.

What aperture / point density do you use for FR1 channel filters versus narrow crystal filters?
L Admin
Editorial addendum: a worked example of aperture choice, since it is the most common source of noisy group-delay plots.

Group delay = −Δφ/(360°·Δf). If the VNA phase has 0.1° of noise and you use a 1 MHz aperture, the delay noise is about 0.1/(360·1e6) ≈ 0.28 ns — larger than the ripple in many filters. With a 10 MHz aperture it drops to 28 ps. Rule of thumb: pick an aperture well below the bandwidth of the features you want to see (e.g. 1/10 of the filter bandwidth), and increase averaging or reduce IF bandwidth rather than widening the aperture past that.

Second check: for a plain 1 m cable with velocity factor 0.7, group delay should be ≈ 4.76 ns and flat. Measuring something simple like that before the DUT verifies your setup.

Question for readers: for wideband filters in radar or 5G, what group-delay variation do you specify across the channel, and how do you measure it in production?

— rfforum 编辑部 / Editorial Team
L Admin
On the editorial ask (wideband radar / 5G filter **group-delay variation** and how to gate it in production):

1. **What we put on the drawing**
- Spec **Δτ across the occupied channel** (sometimes also across the 1 dB / 3 dB BW), not absolute τ — absolute delay is fixture-dominated unless you TRL/de-embed.
- For FR1 channel filters we usually freeze Δτ as a **peak-to-peak** (or max−min) over the passband of interest, with the **aperture written on the test method** (e.g. aperture ≈ BW/10…BW/20, or a fixed MHz value tied to the signal BW).
- Radar / ranging paths: also watch **slope** / linearity of τ(f); a smooth tilt can be equalised, a ripply Δτ becomes range sidelobes / EVM.

2. **Order-of-magnitude habits (not universal limits)**
- Sub-6 channel filters for digital radios: we have shipped with **tens to a few hundred ps** p-p Δτ across the channel when EVM budget was tight; looser links tolerate more.
- Always co-specify with |S21| ripple — a filter that meets |S21| but fails Δτ is still a fail for the modem.

3. **Production measurement**
- Same aperture / point density / IFBW as the qualification method (write them on the traveler).
- Report **relative** Δτ after a fixture thru or de-embed; do not fail parts on absolute delay against an SOLT cable stack.
- Golden filter in the fixture at start of shift: if golden Δτ walks, fix torque/cable dress before sorting DUT lots.
- Temperature: if the product sees outdoors, either measure Δτ at temp corners or budget the temp walk explicitly — cable dress + filter both move.

4. **Quick sanity before trusting a fail**
Replace DUT with airline / known delay line; confirm flat τ and expected absolute delay. Spikes that move when you raise point count are unwrap artifacts (OP’s mistake #2), not the ceramic.

Open: do you fail production on **p-p Δτ**, on a **masked ripple mask**, or only on EVM of the full chain?

— rfforum 编辑部 / Editorial Team